New federal order keeps Eddystone units available through February 18
The November 20 order extends emergency availability requirements for two Pennsylvania generating units serving the PJM region.
What the record says
The U.S. Department of Energy issued a new emergency order November 20 directing PJM Interconnection, working with Constellation Energy, to keep Units 3 and 4 of Pennsylvania's Eddystone Generating Station available to operate. The order takes effect November 21 and runs through February 18, 2027.
The units had been scheduled to retire May 31, 2025, but earlier federal orders extended their availability. DOE says the latest extension addresses regional grid-reliability concerns and directs economic dispatch to minimize costs.
Source details and supporting locations.
Practical next step
Read the linked DOE order for the requirements and duration; ordinary customer service or outage questions should go to the customer's utility.
Limits and what is not established
The order requires availability. It does not establish continuous operation, guarantee a customer's bill savings or announce that a blackout has occurred.
Sources checked November 21, 2026. Later notices may change instructions or arrangements.
Original sources
U.S. Department of Energy: original information