Somerset pumping-station programme reports first refurbishments complete
The Environment Agency’s£11 million programme covers six stations, with further work planned in 2027 and2028.
What the record says
The Environment Agency announced on November 12 that pump refurbishments at Midelney and Huish Episcopi were complete as part of an£11 million modernisation programme covering six Somerset Levels and Moors stations.
The notice schedules Northmoor and Westover work for 2027, with Long Load and North Drain due to be finished in 2028. It describes replacing ageing electric pumps with equipment intended to improve reliability and efficiency and reduce impacts on fish and eels.
The agency says the stations help manage flood depth and duration in winter and support irrigation and nature in summer. It also encourages residents to check flood risk, make a plan and sign up for warnings.
Source details and supporting locations.
Practical next step
Residents can use the Environment Agency’s official flood-risk and warning services.
Limits and what is not established
Completion at two stations does not mean the six-station programme is complete or that flooding is eliminated. The£11 million programme is distinct from other Somerset and national flood budgets; do not add them as a new single award.
Sources checked November 13, 2026. Later notices may change instructions or arrangements.
Original sources
UK government official department: original information